Project · Simi Valley guest house

Detached
ADU construction,
Simi Valley

Residential & ADUs

Overview

An 880 square foot detached guest house in Simi Valley, built from a cleared plot through to final inspection. It has two bedrooms, one bathroom, and an open cathedral ceiling running the length of the living space, which is what took the framing from about one week to three. The job began in January 2024 and passed final inspection at week fourteen.

Location
Simi Valley, Ventura County
Client
Private residential
Size
880 sq ft
Accommodation
Two bedrooms, one bathroom
Built
January 2024, 14 weeks
Status
Completed, passed final inspection

Scope of work

  • Site clearance and grading to a level building pad
  • Footings excavated, formed and reinforced
  • Foundation and slab poured and finished
  • Timber framing to an open cathedral ceiling
  • Roof, windows and exterior finishes
  • Interior trades, kitchen and bathroom fit-out
  • Through to final inspection

Site challenge and execution

An open cathedral ceiling instead of a flat one

The owner asked for an open cathedral ceiling running the length of the living space rather than the flat eight-foot ceiling a guest house this size would normally have. That turns the roof from a surface into structure: it has to carry its loads without a ceiling tying the walls together, so the members, the connections and the bracing are all different.

It cost time rather than difficulty. Framing ran to three weeks against roughly one for a standard flat-ceilinged frame of the same footprint, and week six lost all but three days to rain.

How the job ran

  1. Grading and footings

    January 2024

    The plot was cleared and graded to a level pad, and the footings were then dug, formed and reinforced around the footprint.

    A cleared and graded building pad in Simi Valley, tracked out by machine and ready for setting out
    The pad cleared and graded
    Footing trenches dug and formed in timber around the perimeter of the building footprint, reinforcement laid in the bottom of each run
    Footings formed to the footprint
    Reinforcing steel tied through the formed footings with sheeting laid across the slab area behind it
    Reinforcement tied and the slab area sheeted
  2. Foundation and slab

    to end of January 2024

    The foundation and slab were poured and finished, closing out the groundwork and giving the frame something to stand on.

    The poured and finished concrete slab of the guest house with its edge formwork still in place
    Slab poured and finished
  3. Framing

    weeks 5–8

    Walls and roof framed in timber to the open cathedral ceiling. The framing took three weeks, and week six lost all but three days to rain.

    The timber frame of the guest house standing on its slab, wall studs and rafters up and the gable end taking shape
    The frame going up
    The open cathedral ceiling seen from inside the frame, rafters and ties against open sky before the roof went on
    The cathedral ceiling framed, before the roof
    The completed timber frame of the guest house with its roof structure closed and the window openings formed
    Framing complete at week eight
  4. Trades, finishes and final inspection

    weeks 9–14

    Roof, windows, exterior finishes and the interior trades ran alongside each other to the end, and the building was handed over for final inspection at week fourteen.

    The finished guest house from the front, its covered porch, gable end and painted siding complete above a gravel apron
    The completed guest house
    The completed guest house seen across the lot, showing its full length and the open ground it was built on
    The same ground as the first photograph
    The finished living space of the guest house, the cathedral ceiling running its full length above plain white walls
    The cathedral ceiling, finished
    The finished kitchen of the guest house, fitted cabinets and appliances beneath the open ceiling
    Kitchen under the open ceiling
    The finished bathroom of the guest house, tiled with a vanity unit and a window above
    The bathroom

Services on this project

Questions about work like this

How long does it take to build a detached ADU?

An 880 square foot detached guest house built by EMAE & Sons Inc in Simi Valley passed final inspection fourteen weeks after the site was cleared, including three weeks of framing for an open cathedral ceiling and a week largely lost to rain. Groundwork, access and weather move that figure more than the size of the unit does.

What is an open cathedral ceiling in an ADU?

An open cathedral ceiling follows the pitch of the roof rather than being closed off flat, so the room is open to the ridge. EMAE & Sons Inc framed one the full length of an 880 square foot guest house in Simi Valley. It takes longer to frame than a standard flat ceiling, because the roof has to carry its loads without a ceiling tying the walls together.

Can a guest house be built on an empty part of a lot?

Yes. EMAE & Sons Inc built an 880 square foot detached guest house in Simi Valley on cleared open ground beside the existing house, with its own footings, slab and entrance. The building stands independently rather than attaching to or converting any part of the main house.